How long does a building permit take in Austin?

Updated November 11, 2026 · Built from official fee schedules and city permit records

28 days
median wait, residential building permits
8,030
permits measured
77 days
slowest 25% took at least

Austin issues simple repair permits within days, but anything that needs residential plan review usually takes one to four months.

Wait time by permit type

PermitPermits measuredFastest 25%MedianSlowest 25% start atSlowest 10% start at
Foundation repair1,011same day2 days6 days12 days
New house2,24826 days53 days116 days285 days
Swimming pool1,02532 days62 days123 days300 days
Remodel or addition1,23335 days66 days130 days287 days

Figures cover every building permit the city issued from November 1, 2025 to October 31, 2026, measured from application date to issue date. The median is the middle permit: half were faster, half slower. The slowest 25% usually had plan corrections or a full plan review.

How to get your permit faster

More Austin permit guides

Sources

This is an independent guide built from public records. It is not affiliated with the City of Austin Development Services Department. Fees change, and the city calculates your final fee when you apply; confirm the amount with the city before you budget.

Common questions

How long does it take to get a building permit in Austin?

The median residential building permit took 28 days; new houses 53 days and remodels 66 days.

Which Austin permits are fastest?

Repair permits such as foundation repair, with a median of 2 days.