How long does a building permit take in Chicago?

Updated November 11, 2026 · Built from official fee schedules and city permit records

6 days
median wait, residential building permits
31,361
permits measured
29 days
slowest 25% took at least

Chicago has two speeds. Express Permits (roofs, porches, fences, solar) are usually issued within days. Standard Plan Review for new homes and larger renovations takes one to several months.

Wait time by permit type

PermitPermits measuredFastest 25%MedianSlowest 25% start atSlowest 10% start at
Re-roof1,305same day1 day4 days12 days
Fence965same day1 day5 days13 days
Detached garage877same day4 days29 days87 days
Deck or porch7393 days6 days13 days25 days
Rooftop solar1,7996 days9 days15 days26 days
New house29243 days66 days121 days184 days
Remodel or addition2,15244 days81 days147 days251 days

Figures cover every building permit the city issued from November 1, 2025 to October 31, 2026, measured from application start date to issue date. The median is the middle permit: half were faster, half slower. The slowest 25% usually had plan corrections or a full plan review.

How to get your permit faster

More Chicago permit guides

Sources

This is an independent guide built from public records. It is not affiliated with the Chicago Department of Buildings. Fees change, and the city calculates your final fee when you apply; confirm the amount with the city before you budget.

Common questions

How long does it take to get a building permit in Chicago?

Express permits often issue same day or within a week. The median renovation took 81 days, and new houses 66 days.

What is the fastest permit path in Chicago?

The Express Permit Program, for repairs and simple projects.