How long does a building permit take in Fort Worth?

Updated November 11, 2026 · Built from official fee schedules and city permit records

18 days
median wait, residential building permits
4,962
permits measured
32 days
slowest 25% took at least

Fort Worth is fast for a big city. Remodels are often issued within a week and new homes within three weeks.

Wait time by permit type

PermitPermits measuredFastest 25%MedianSlowest 25% start atSlowest 10% start at
Remodel or addition1,1271 day5 days14 days41 days
New house3,08315 days20 days35 days75 days
Home addition27614 days21 days44 days89 days

Figures cover every building permit the city issued from November 1, 2025 to October 31, 2026, measured from file date to issue date, for permits currently in Issued status. The median is the middle permit: half were faster, half slower. The slowest 25% usually had plan corrections or a full plan review.

How to get your permit faster

More Fort Worth permit guides

Sources

This is an independent guide built from public records. It is not affiliated with the Fort Worth Development Services. Fees change, and the city calculates your final fee when you apply; confirm the amount with the city before you budget.

Common questions

How long does it take to get a building permit in Fort Worth?

The median residential permit took 18 days; new houses 20 days.

How are these wait times measured?

From the filing date to the issue date, for permits still showing Issued status in city records.