Groundtip Permit Cost Guide

How long does a building permit take in San Antonio?

Updated November 11, 2026 · Built from official fee schedules and city permit records

1 day
median wait, residential building permits
18,659
permits measured
7 days
slowest 25% took at least

San Antonio issues most small residential permits the same day. New homes take one to four weeks, and accessory dwelling units take longest.

Wait time by permit type

PermitPermits measuredFastest 25%MedianSlowest 25% start atSlowest 10% start at
Re-roof4,412same daysame daysame daysame day
Fence1,050same daysame day2 days9 days
Home addition408same daysame day3 days23 days
Foundation repair3,238same day1 day4 days9 days
Swimming pool281same day1 day4 days8 days
New house3,5926 days9 days28 days86 days
Adu / backyard cottage5339 days68 days146 days187 days

Figures cover every building permit the city issued from November 1, 2025 to October 31, 2026, measured from submittal date to issue date. The median is the middle permit: half were faster, half slower. The slowest 25% usually had plan corrections or a full plan review.

How to get your permit faster

More San Antonio permit guides

Sources

This is an independent guide built from public records. It is not affiliated with the San Antonio Development Services Department (DSD). Fees change, and the city calculates your final fee when you apply; confirm the amount with the city before you budget.

Common questions

How long does it take to get a building permit in San Antonio?

Most small permits are issued the same day. New houses took a median 9 days.

Why do ADU permits take longer in San Antonio?

They need full plan review; the median was 68 days.