How long does a building permit take in Seattle?

Updated November 11, 2026 · Built from official fee schedules and city permit records

62 days
median wait, residential building permits
4,148
permits measured
155 days
slowest 25% took at least

Seattle is one of the slower big cities for new homes and ADUs, because they go through full plan review and often land use review too. Smaller alterations are much quicker.

Wait time by permit type

PermitPermits measuredFastest 25%MedianSlowest 25% start atSlowest 10% start at
Remodel or addition2,3621 day13 days64 days138 days
Deck or porch2072 days29 days75 days213 days
New house878115 days159 days212 days276 days
Adu / backyard cottage509107 days183 days294 days554 days
Demolition27029 days70 days138 days223 days

Figures cover every building permit the city issued from November 1, 2025 to October 31, 2026, measured from application date to issue date. The median is the middle permit: half were faster, half slower. The slowest 25% usually had plan corrections or a full plan review.

How to get your permit faster

More Seattle permit guides

Sources

This is an independent guide built from public records. It is not affiliated with the Seattle Department of Construction and Inspections (SDCI). Fees change, and the city calculates your final fee when you apply; confirm the amount with the city before you budget.

Common questions

How long does it take to get a building permit in Seattle?

The median residential permit took 62 days. Remodels took a median 13 days; new houses 159 days.

Why do Seattle ADU permits take so long?

ADUs usually need full plan review and correction cycles. The median ADU permit took 183 days.