Groundtip Permit Cost Guide

What does a building permit cost in Seattle?

Updated November 11, 2026 · Built from official fee schedules and city permit records

4,408
residential building permits issued, last 12 months
62 days
median wait
$3,643
permit + review fee on a $100k project

Seattle building permits cost from a few hundred dollars for small work to $10,000 or more for new houses. The fee depends almost entirely on the value of the work.

How the fee is calculated

Seattle prices building permits from the project's value. SDCI turns the value into a development fee index using Table D-1 of the 2026 Fee Subtitle (for example, $325 for the first $1,000, then $1.60 per extra $100 up to $25,000). You pay that amount once as the permit fee and once more as the plan review fee. Projects that qualify as subject to field inspection (smaller work reviewed in the field instead of in full plan review) pay only 40% of the index for plan review. Fees went up about 18% on January 1, 2026.

Fee by project value (full plan review)

Project valueDevelopment fee indexPermit + plan review fee
$1,000$325.00$650
$10,000$469.00$938
$25,000$709.00$1,418
$50,000$1,096.50$2,193
$100,000$1,821.50$3,643
$250,000$2,984.00$5,968
$500,000$4,859.00$9,718
$1,000,000$8,359.00$16,718

Typical costs by project

ProjectPermitsMedian valueEst. feeMedian wait
New house878$381,536$7,948159 days
Adu / backyard cottage510$230,846$5,674183 days
Remodel or addition2,362$50,000$1,53513 days
Deck or porch276$22,059$92829 days

More Seattle permit guides

Sources

This is an independent guide built from public records. It is not affiliated with the Seattle Department of Construction and Inspections (SDCI). Fees change, and the city calculates your final fee when you apply; confirm the amount with the city before you budget.

Common questions

How much is a building permit in Seattle?

It depends on project value. A $100,000 project pays about $3,643 in 2026 permit and plan review fees; a $25,000 project about $1,418.

How long does a Seattle building permit take?

The median residential building permit took 62 days from application to issue over the last 12 months.